Work continues on pool project
A further step has been taken on the project to renovate the City of Red Oak’s municipal pool.
At the regular meeting of the Red Oak City Council Dec. 2, city administrator Brad Wright said some of the smaller portions of the concrete work have been completed.
“They did their first pour, which was the floor of the surge tank, and the adjoining floor between the old and new pool. They’re planning on more concrete work this week, and they are anticipating a larger cement pour,” Wright said.
Plans still call for the contractor, Ricchio, Inc. to continue with cement work on the project through the winter season.
“The schedule they have presented anticipates pouring concrete every month throughout the winter. Naturally, extreme weather conditions will alter their schedule, however they appear comfortable and experienced with winter construction,” said Wright.
One benefit to the project so far has been the much milder temperatures and the lack of measurable snowfall in the area.
The mild weather thus far has certainly been to the contractor’s advantage. We are hopeful that it will continue,” commented Wright.