Early childhood center renovation plans approved

The Red Oak School Board is moving forward with renovations to the Washington Intermediate building, soon to be rebranded as the Early Childhood Development Center.

At the regular school board meeting Aug. 26, the board met with architect Daric O’Neal with Alley Poyner Macchietto Architects, who brought bid documents for the board to review and approve.

“We have put this into five different phases of construction. Phases two through five are bid alternates. The only thing we are suggesting awarding on bid day is phase one,” O’Neal said.

The first phase includes the four north classrooms of the existing Washington building, and the four east classrooms of the new portion of the Washington building.

“They have fairly different scopes to them. On the old Washington side, we’re taking the four classrooms and renovating them to the child care component. Rehab includes carpet, ceilings, lighting, heating and cooling, new cabinetry, and sinks. We plan to do a little bit of insulation work on the north wall as well,” commented O’Neal.

Phase two is all heating and cooling for the rest of the old Washington building, including the gym, classrooms to the south of the building, the media center, and other interior classrooms. The system would be a VRF type of system.

Phase three includes the south classrooms, to be occupied by the pre-K program for the upcoming year.

“Those four classrooms get the carpets, sinks, cabinets, and LED lighting to match the classrooms we’re doing on the north side of the building. The heating and cooling is covered under phase two,” said O’Neal.

Phase four includes miscellaneous portions of the project, including a revised entry and reception area, with the southeast door the main entrance to the building., new doors, and windows. The fifth and final phase is an alternate heating and cooling system for new Washington.

O’Neal said the projects would need to be done in order. The first phase has a substantial completion date of Dec. 1. Bids for the project will be reviewed on Sept. 12, and then shared with the board at a special Sept. 16, meeting.

There will be one general contractor for the project, with Boyd Jones serving as the construction manager and representative. Phase one is estimated at $700,000, with the remaining projects totaling $1.5 million.

The board approved the bid documents for the early childhood center as presented.