Extra cost added to delayed historic designation
Downtown Red Oak inches closer to becoming a historic district but not without a few hiccups.
During November 2012, the Red Oak City Council approved $40,000 to Alley Poyner Macchietto Architecture for the research and site inventory work required to attain a spot on the National Registry.
Daric O’Neal of Alley Poyner came before the Council last week saying the State Historical Preservation Organization did acknowledge downtown Red Oak qualifies for a historic district, which would open up possibilities for development tax credits for future renovation projects. However, another component needs to be added to the proposal before a nomination can be made.
O’Neal requested $15,000 from the Council for the research and time needed to incorporate the historical significance of the Murphy Calendar Company into the downtown histori cal district materials, per the state’s request.
“We went over downtown Red Oak and spent a lot of time at the history center researching this and we just did not anticipate the state coming back and saying you need to work the Murphy Calendar Company into the nomination for the downtown,” O’Neal said. “That’s already a building listed individually on the register of historic places and it’s outside of our downtown district boundaries.”
The state’s request will not alter the district boundaries, which are from Washington to Hammond and 6th Street to Broadway, to include the calendar company. Rather, information on the historical significance the company had on buildings within the district will be researched and included in the proposal.
O’Neal said an obvious example of this is the post office, which he said was built to be large enough to handle the mail volume from the calendar company. Other connections could include businesses that began in connection with the calendar company or former employees of Thomas D. Murphy who started downtown businesses.
Councilmembers Larry Barnett and Jeanice Lester expressed concern with the extra cost involved in the proposal because the process still requires another $10,000 for the nomination fee.
City Administrator Brad Wright said there is a possibility for grants to go toward the nomination fee, but finding ways to meet the state’s new request at a limited price should be examined.
O’Neal said one option is contacting the historian who helped put the calendar company on the national registry during the early 2000s to borrow some of her research rather than starting from scratch. This type of request would have to come from the City, though, O’Neal said.
No formal action was taken on the matter at last Monday’s meeting; O’Neal and Wright will work together on other possible solutions.
O’Neal also spoke at the meeting on the next step in Red Oak’s downtown master plan.
For another community, Alley Poyner consultants created a graphic of development standards, including everything from windows and awnings to color schemes and stylistic details for downtown storefronts in a historic district.
Through a series of public meetings, O’Neal said these types of standards could be adapted for Red Oak and added as an overlay to the City’s zoning codes.
“This is critically needed,” Wright said. “With the (façade project) we’re taking on in this next year, we are putting a lot of investment back in to getting those buildings historically correct. Under our current code, there is nothing to prevent building owners from … doing whatever they want to do.”
This component of the master plan would cost the City $15,000, according to O’Neal, who will present a formal proposal at the next Council meeting.
In other business, the United Farmers Mercantile Cooperative will be expanding through a Tax Increment Financing reimbursement from the City.
UFMC Manager John Pruss said they intend to build a $4.6 million dry fertilizer building next to the railroad tracks west of the storefront.
The Council directed Wright to draft a development agreement to be discussed at the next meeting April 1.