Stanton School Board begins next steps in renovation project

The Stanton School Board is ready to begin the next steps of its renovation project.
Stanton Community School District Public Measure Q/A, which authorized the board to contract indebtedness and issue general obligation bonds in an amount not to exceed $5,325,000 for remodeling and improvements, and Stanton Community School District Public Measure Q/B, authorizing the board to levy annually a tax exceeding $2.70 per $1,000 valuation, but not exceeding $4.05 per $1,000 valuation to pay the principal of and interest on bonded indebtedness both passed with a two-thirds majority in the Nov. 4 general election.
The board met with Kevin Schluckebeir, regional program manager with KPE Architecture at its meeting Nov. 12 to discuss the next phase of the project now that the bond issues have passed. Discussion opened reviewing the plans, with Schluckebeir stating based on community feedback, may see some slight adjustments, such as the clerestory skylight providing natural light in the school lobby, and whether that project may become an alternate among the steps of the project.
“That’s the natural light that also gets to this interior bubble classroom that is elementary. So I leave that up to you guys. That could be kind of the last item included as you look at a base bid and some additives if there’s money available. It’s higher on my desire list because the kids are in one particular classroom receiving that natural light all day. The high school, I have less concern because you’re in and out throughout the day moving to classes,” explained Schluckebeir.
Also discussed was the addition of some type of cover a little bit farther out on the walkway on the approach to provide shelter for the kids if they were outside in the rain. It was not included in the original designs, but Schluckebeir said they hadn’t done a lot of legwork on exterior design improvements and a canopy would be easy to incorporate if the board chose to include it on the project.
Schluckebeir urged the board to check into its electrical ratings, as some of the improvements would require a strong power source.
“At a recent Stanton City Council meeting there was quite a discussion about the electrical needs and what it will need to do for upgrades. I know it’s been brought up before, but if someone would want to reach out to the city, now would be a good time because they’re looking at doing some other things. I don’t know if there would be any cost savings or whatnot, but it would be good to know how all that is going to affect electrical needs,” advised Schluckebeir. “There was a comment too about the transformer out there not being big enough. If that is the case, the City of Stanton works with the REC, and since they’re looking at doing some other electrical upgrades, it might be beneficial to do an upgrade to the transformer, if you need to, at the same time. The concern is basically over adding AC to the channel, and whether the transformer has enough capacity for whatever we would need.”
The members of the board agreed to get further information on the transformer for Schluckebeir to review.  As the plans move forward, Schluckebeir said the first stage will be a meeting with all the staff to get their thoughts on the needs, the requirements, the flow, then bring that information to the board with some potential options for discussion that in turn would be taken back to the staff. Schluckebeir anticipated at least one meeting on the project before the Christmas break.
KPE will design the plans with the school’s input, and intermediate deadlines would be discussed, as the building was likely going to be occupied during that period and before the project was put out for bid.
“Contractors look at it for up to four weeks, but realistically, it usually only takes them a couple of weeks, and then they give us a number. Then you proceed on with the build on the lowest reasonable contract. The board would then need to decide if it wants to proceed with a contractor-led construction management. The contractor, at some point during our design phase that we’re working on together, will give you a guaranteed maximum price for the scope that’s involved. Then we finish design, and they can do early packages. As long as the scope doesn’t change, that that’s your price,” commented . Schluckebeir.
Schluckebeir added the district could either contract with the general contractor in a design, bid, build format, who would then contract with all the subcontractors including chemical, electrical, flooring, and ceiling. The second option was construction management at-risk.
“This would mean you have a limited cap on your funds. You hire a construction manager, and you’re hiring your builder through qualifications. Now, the State of Iowa in the last two years has put strict criteria on this one. We would be working with your legal team, and it could be a two to eight month process. Typically, it’s about two months. We just did a project with Glenwood and the process only took a couple of months,” stated Schluckebeir. You would have to advertise the project and put out a request for qualifications. Anyone in those next 13 days, which is the minimum it has to be out on the street and advertised, can provide you their qualifications. After there is a review of those proposals, we ask for a request for proposal with more detail. So I really don’t mind having a short turnaround on the RFQ. It’s basically asking, do they have the qualifications to do this type of job? This is their kind of general marketing. So if there’s not a lot of detail, they can get that to us pretty quick. An RFP is more specific to you, to this project, and how do we move forward, and how are they going to propose to work with you and for you throughout the process. Both KPE and the school’s attorney can work with the district through this process.”
If the district worked with the general contractor, Schluckebeir said the contractor would have a better understanding of the goals, the concerns, and the security risks, up front, and help massage his proposal to make sure that the flow of the construction is going to work for all of the parties. Construction management at-risk is also responsible for a guaranteed maximum price. So their prices matter as KPE and the district are doing design and making decisions, but it still came down to the market in four months when the project was put out on the street for bids. Under at risk, the contractor is at risk when they gave the district the number for the project scope.
Schluckebeir also urged the board to begin advertising right away, as it has to be published for a minimum of 14 days, which would give KPE a little bit of time to work on the next document for the request for qualifications.
A third option the district could choose is construction manager as agent, which would be not at risk, and with no guaranteed maximum price. The process of the construction is the same.
“You get them on quick. Under this scenario, they are considered professional services, like your architect. You can interview and you can pick someone that you’ve used. You can do your own select shortlist. You have flexibility to pick that person because it’s considered professional services. All of the sub work has to be bid if it’s over $35,000. They can self-perform some work. If they are going to try and do so, they would put a bid in 24 hours before anybody else does so that you take that conflict potentially off the table,” Schluckebeir commented. “There is some flexibility where they can actually perform work. Otherwise, they’re more for oversight, and they’re helping with the budgets all the way through, but they are tied to them in a guaranteed max. The advantage of design-bid-build and CM as agent is there isn’t a legal process in the middle of this. That stuff happens in your bid days later on. But it does give you the ability to do early packages, do some of those things in segments because they’re going to give you kind of the overall budget price.”
While it isn’t a huge project, Schluckebeir said it was a complex one because the buildings were going to probably be occupied during the part of the construction.
“Whether that’s one season, whether that’s two seasons, is yet to be determined, but the shorter the season, the better the price we’re going to get. I want to do everything we can to accelerate every part of the project to help on the price and help the team that is working together in creating that structure. So to me, the CM at-risk has some advantages for that guaranteed max. You’re a little bit more at-risk if you go as agent, but it does accelerate getting a contractor on board. There’s a way around in each of these to make it successful that will help you. It’s more where do you feel comfortable moving forward, because there are advantages and disadvantages to each one of these. Design, bid, build, or contractor at risk, either one, they’re basically bidding the maximum that we’re going to pay, so it’s pretty similar in that regard.”
Schluckebeir also said the district would need to set up some funding in a contingency fund.
“You also have furniture, you have some of these other things we need to make sure that are either in that budget elsewhere or other budgets that are accounted for. If you remember back on the last project, we talked about total project costs versus construction costs to make sure that you have enough contingency, not necessarily in this package, but in other buckets that you can utilize so that you’re protected. We’re still going to do the same thing from there to make sure we have these things accounted for,” said Schluckebeir.
The board took no further action on the project at the meeting.