The Montgomery County Board of Supervisors has acted on a decision for an engineering firm to oversee the potential construction of the Summit Carbon Solutions pipeline.
Supervisor Mike Olson felt that the county needed to make a decision, and quickly, on some sort of representation.
“I feel that we need to move on this as soon as possible and get someone in here who knows what’s going on and has dealt with this before to help us with a resolution or an ordinance, because ordinances don’t happen overnight,” Olson stated. “It’s going to take a considerable amount of time to author an ordinance for our county. We’ve looked at three firms now.”
Supervisor Donna Robinson said she was in agreement that the county should make its move.
“We’ve had three presentations from companies, one of them so far back as last October. We’ve spread it out and it’s hard now to go back and recall everything that was said. Snyder & Associates was the most recent firm we’ve met with. They are somewhat local and have something of a vested interest in this project. It’s not new to them, and I was extremely impressed with the information they gave us,” commented Robinson.
Supervisors Chair Mark Peterson said when it came to draft ordinance, that he had received a copy of an ordinance for potential use in constructing a draft in Montgomery County.
“They’ve spent a lot of time and money getting theirs put together, and zoning administrator Barry Byers has it for further review,” Peterson said.
Robinson said she received information from Kristina Paradise, representing Snyder & Associates and had received a draft of a resolution that was drafted in Pocahontas County for the county to review as well. Olson reviewed the resolution and said it had pertinent information the county could use.
“The resolution went into detail on depth of the pipeline, topsoil removal, and the multiple other items that we want to make sure are taken care of if a project comes to fruition,” said Olson.
Still, Olson reiterated that no matter what, if the State of Iowa stepped in and put its own regulations in effect, any ordinance or resolution approved by the supervisors would be rendered moot. Robinson said she had received further information from Paradise that confirmed that situation.
“Other than putting an ordinance in place and hiring an engineering firm to oversee it, that’s all we can do,” advised Robinson.
Rather than waiting, Robinson proposed the supervisors go into an agreement with Snyder & Associates as the engineering firm representing the county on the pipeline project moving forward.
“The reason that sounds somewhat vague is because I had some questions and have sent questions to Alan Armstrong in Page County, and a letter of intent is not necessarily the same as a contract, so this motion would simply state that Snyder is the company we’re going to work with, and then we’ll figure out what the next step is,” said Robinson.
The supervisors unanimously approved entering into an agreement with Snyder & Associates as the county’s pipeline representative.