Major projects to be completed in 2014

Montgomery County Fair Building

After more than 60 years, the livestock barn area at the Montgomery County Fair Grounds will be getting a facelift. 

After the 2013 fair, three barns, which housed hogs, rabbits and poultry, along with a wash station, were demolished and a new 80x180 foot barn and show arena is being built. 

Dirt work began on the new building during the fall, and as of a week ago, the metal frames began to go up. 

Fairboard member Roger Vial said the building will likely be enclosed during the winter and the interior will be completed during the spring to be ready for the 2014  fair. 

Interior work ranges from laying concrete to installing electricity and assembly livestock pens and arena seating. 

“The harvest went longer than planned this year so that set us back a bit at the beginning, but we’re on track,” Vial said. “The show has to go on. We have to have a place for the kids to show their projects. So it will be ready to go by June.”

The new building will have an open barn area, fit to house a variety of livestock, which Vial said is a necessity for the changing trends in 4-H projects. In past decades, larger animals, like cattle and hogs were most popular. As of lately, there has been an increase in rabbits and poultry. 

Also in the building will be a new show arena. The arena in the beef barn will act as a back up in case shows overlap. 

The new building cost the fairboard around $450,000, most of which was raised through donations, Vial said about $150,000 is fairboard debt. He added all future fundraising efforts through the fairboard will go toward retiring the building’s debt. 

“I just encourage people to continue to support 4-H and FFA in the county,” Vial said. “This building really is an investment in our future.”

 A&M Green Power 

At an estimated price tag of about $5 million, A&M Greenpower’s newest dealership on Highway 34 is still expected to open this summer. 

Director of Finance Randy McCunn said Monday they hope to have the already-erected steel framed enclosed in the next couple months before moving inside to work on the 45,000 square foot building. 

The new facility will include an 80x225 foot showroom including parts storage and sales offices, 100x225 workshop, 40x60 washroom, 40x65 tool storage and 7,200-square foot mezzanine that will house a conference room and more storage. McCunn also said the agriculture equipment provider’s recent merger with Barker Implement will have no affect on the Red Oak building. 

He also said there will be an undetermined number of new jobs created by the bigger dealership and that those positions will be filled in early summer. 

The City of Red Oak is helping fund construction in terms of tax rebates that will amount to about $450,000 over the next four years. 

 Stanton Viking Center

Stanton’s $3.2 million Viking Center is expected to be completed first, as early as spring 2014. 

The 140’ x 112’ two-story, 25,000 square foot structure which will house a public library, preschool and walking track on its upper level, and a gymnasium, community room, wellness/recreation center, and FEMA-approved storm shelter on its lower level. This shelter would accommodate 623 people in an emergency. Handicapped accessible entranc es will be available on both levels. 

“This is another way we keep trying to make our community a better place to live and raise a family,” said Mickey Anderson, co-chair of the “Stanton Friends”, a steering committee formed in 2008 that has organized the project. 

The building sits on land which was donated to the City of Stanton, adjacent to the school and the Greenbelt Trail, making it easily accessible to area residents and students. 

Co-chair Chuck Truka is proud that “green” technology and energy-saving concepts have been utilized. 

“The building will be heated and cooled by an EER 15 geothermal system, and materials for insulation, doors, windows etc. exceed Iowa energy codes,” he said.

Funded by donations from more than 400 individuals, families and foundations, as well as several grants, memberships will be counted on to meet the cost of day-to-day operations. 

Anderson said this project is another example of Stanton’s unique growth. 

“Over the past 20 years or so we have acquired land and built 30 spec. houses in Stanton,” he said. “In the last year alone, about 40 homes have sold in the Stanton tax district. The city has erected a new water tower, improved sidewalks, constructed a new fire station, and created the Greenbelt walking trail. This project is one more piece to this puzzle.”

Villisca Gym

With a target completion date of July 2, Villisca’s new gymnasium promises to benefit both school students and the public alike. 

The facility under construction south of Enarson Elementary School is owned by the district and will house a full-size gymnasium with six adjustable basketball hoops and volleyball courts. There will also be a three-lane walking track, and a fitness room of about 1,400-square feet equipped with weight equipment, elliptical machines and treadmills. 

The Villisca Youth Leagues will be able to use the building for their activities, and it will also be available to the public for a small fee at times when the school is not using it.

“Our plan is to have it open to the public from about 5 - 7:30 am and 5 - 10 pm,” said Stone. “We envision parents wanting to come in and shoot hoops with their kids, older folks wanting a warm, safe place to walk or use the equipment. It will be set up on a f.o.b. (electronic security) card system. There will be a minimal fee just in order to recoup the district’s cost for projected utilities. We are certainly not in this to make money, but rather to provide a service.” 

The project will cost $1.5 million with a third of the cost paid for by the district’s one-cent sales tax. The remaining $1 million will be paid for through a 10-year bond. 