Citizens ask about school facilities options

Red Oak Community School District residents had a chance to offer their input at the final school facilities meeting.
The board, along with Alley Poyner Maccietto architect Daric O’Neal and Boyd Jones representative Mark Phfister, met with the public at the Wilson Performing Arts Center last Thursday.
Superintendent Tom Messinger opened with an overview of the district’s financial status.
Messinger said the district had discussed ways to use their money as efficiently as they could, as the district is within three years of exceeding how much money it is allowed to spend.
“Finding ways to cut money means looking at everything, but realistically, 79 percent of our general fund budget was paid to staff salaries and benefits. That means staff reductions lead to the most savings,” Messinger said.
Messinger said the only other option was to cut programs, or both. Reducing the number of campuses, Messinger said, would be key in making the district more efficient.
Facilities options
O’Neal once again shared three potential options for the district when it came to renovation of the buildings. For the first option, at an estimated cost of $13 million, retains use of four of the five buildings, except for Webster, which was closed during the summer. The option only handles the critical repairs.
The second option, at an estimated cost of $22 million, moves the district to a two-building campus, eliminating Washington and the middle school. The two-building plan would then turn Inman Primary into a pre-kindergarten through sixth grade building. The high school would then become a grades 7-12 building.
The third scenario maintains Inman and the high school, with the same renovations, at a cost of $34 million, and includes some demolition costs.
The meeting included a question-and-answer session, during which members of the crowd submitted questions to the Red Oak School Board.
One question asked whether the district would have a competition gym, rather than a practice facility. School board member Bret Blackman advised it was an option.
“I think from a pride standpoint, it’s an important option to consider,” Blackman said.
O’Neal also commented on the possibility, saying while he agreed with the idea there was only so much money available to spend.
“That $34 million plan is the maximum the community can support. We’ve talked, myself and the Boyd Jones crew, about taking out a practice facility and plugging in a competition facility should we have great numbers on bid day. The athletics committee agreed that a competition gym was an incredible value in promoting the community, but a practice facility had incredible value for the student athletes. I think it all comes down to the money available to spend,” O’Neal said.
Even if the district didn’t expand to a full competition gym, the gym itself at the high school was competition size, it call came down to the number of seats to be considered a full competition gym.
Another question was asked about the fate of the buildings, were the district to go to a two-campus facility. Would the district be able to save demolition costs by selling the buildings. Griffen said it was an option.
“That is the first thing we would want to do. Find a repurpose of the buildings. It’s something we need to look at as a board. But we definitely don’t want to leave the buildings standing and unused,” commented Griffen.
Demolition of the middle school and the Webster building were included in the $34 million project package. It did not include the demolition of Washington.
Another question asked whether any plans had been made if there was the closing of another district and those students were taken in by the Red Oak District.
“The current plan can take in additional students. It could easily add 10 students per grade level with no problem. The first building to feel the squeeze would be at Inman. But there is flexibility to add students. However, the first priority of the plans is to benefit students of the Red Oak District first,” O’Neal said.
Messinger elaborated that the reduction in buildings would eliminate the need for multiple teachers at the school sites, and eliminate the travel time of teachers, all which would save the students money.
The final question asked of the board was which plan was their preference, if they were to vote that night. Board member Kathy Walker was in favor of option three. Griffen’s preference was either option two or option three, or something in the middle. Mark Johnson’s choices were either option two or option three. Bryce Johnson and Bret Blackman were also in favor of option two or three, or something in the middle.
The board makes its final decision for an option at their Dec. 12 board meeting. The public is invited to attend and make comments.

The Red Oak Express